13 Years After the Flood:

Slow Implementation of Flood Protection Measures Draws Criticism

Nachrichten
26.11.2026 12:06
Porträt von Krone Oberösterreich
Von Krone Oberösterreich

During this year’s drought, flooding was not an issue in Upper Austria, but it will become one again. This is because climate change is intensifying extreme weather events. The State Court of Auditors has scrutinized flood protection measures in the Eferding Basin and identified several areas for criticism.

“But although the political advisory board for the flood protection project was established as early as October 2013, the project remains unfinished even after about 13 years,” says Court of Auditors Director Rudolf Hoscher, addressing the main point of criticism. The auditors acknowledge that a swift response was made in 2013 and that flood protection measures were approved for the Eferding Basin, where eleven municipalities were affected by the flooding. However, implementation proceeded slowly thereafter.

Enforcement measures should also be reviewed
The Court of Audit views it critically that the structural flood protection measures in the Eferding Basin have not yet been implemented. “The State of Upper Austria should utilize all possibilities for the rapid implementation of flood protection measures and support mutually agreed-upon solutions in the process,” says Hoscher. “The granting of coercive powers—as a last resort—should nevertheless be examined on a case-by-case basis,” adds the LRH director.

Dangerous Special Funding
The auditors view the fact that the State of Upper Austria pledged special funding in the spring of 2025—and de facto also covered the municipalities’ costs—as a risk: “We view this 100-percent coverage of the municipalities’ share of the costs critically. Based on the precedent set in the Eferding Basin, stakeholders in future flood protection projects could demand that the State of Upper Austria cover 100 percent of the costs.”

One plan is still on paper, the other is already digital
The State Court of Auditors also demands that the legally valid zoning plan be implemented digitally; currently, it still exists only in paper form. It could then also be “merged” with the hazard zone map, which is already available in a valid digital version. 

42,000 properties affected
“The address, building, and housing registry must also be integrated into the DORIS system. It provides a basis for risk assessment and the identification of potential hazards. This applies above all to the approximately 42,000 properties located in one of the three hazard zones,” the Court of Auditors states.

This article has been automatically translated,
read the original article here.

Loading...
00:00 / 00:00
Abspielen
Schließen
Aufklappen
kein Artikelbild
Loading...
Vorige 10 Sekunden
Zum Vorigen Wechseln
Abspielen
Zum Nächsten Wechseln
Nächste 10 Sekunden
00:00
00:00
1.0x Geschwindigkeit
Loading
Kommentare Banner - Die Stimme Österreichs

Willkommen in unserer Community! Eingehende Beiträge werden geprüft und anschließend veröffentlicht. Bitte achten Sie auf Einhaltung unserer Netiquette und AGB. Für ausführliche Diskussionen steht Ihnen ebenso das krone.at-Forum zur Verfügung. Hier können Sie das Community-Team via unserer Melde- und Abhilfestelle kontaktieren.

Hinweis in eigener Sache: Das krone.at-Forum präsentiert sich ab sofort in neuem Design! Wir freuen uns über konstruktives Feedback. Damit die Diskussionen in den Kommentarbereichen beim jeweiligen Thema bleiben, können Sie uns Rückmeldungen hier hinterlassen.

Kostenlose Spiele
Vorteilswelt

Magazine der Kronen Zeitung