In record time
Automatically saved design
The serious damage to the south portal of the Schmitten Tunnel in Zell am See, which was only discovered at the end of 2023, has been repaired in record time and the risk of collapse averted. The final date for the completion of all external work has now also been set earlier than planned.
The renovation of the Schmitten Tunnel will be completed on November 22 - 20 days earlier than originally estimated. Traffic has been flowing unhindered through the 5,000-metre-long tube again since the end of June.
Rapid implementation reduces closures
The renovation work at the south portal of the Schmitten Tunnel can be completed earlier than planned. The outer area above the tunnel ceiling was recently restored.
It is not the construction work but regular tunnel maintenance and cleaning that will require a temporary closure of the tunnel from October 8 to 10.
Finally, the outdoor facilities above the tunnel have been restored. The earth for the meadow is back in its original place. When everything is ready in November, skiing on the practice slope can start again on time.
This article has been automatically translated,
read the original article here.








Da dieser Artikel älter als 18 Monate ist, ist zum jetzigen Zeitpunkt kein Kommentieren mehr möglich.
Wir laden Sie ein, bei einer aktuelleren themenrelevanten Story mitzudiskutieren: Themenübersicht.
Bei Fragen können Sie sich gern an das Community-Team per Mail an forum@krone.at wenden.