Long controversial

New 380 kV line in Salzburg goes into operation

Nachrichten
04.02.2025 13:30

After an approval period of 77 months and a construction period of five years, the commissioning of a new electricity supply system in the federal state of Salzburg began these days. 

The first of two 380 kV systems of the so-called Salzburg line between the Kaprun and St. Johann substations has already been put into operation. Further stages of commissioning will follow by April. The investment volume for the new, more powerful power line is around one billion euros.

This article has been automatically translated,
read the original article here.

Porträt von Salzburg-Krone
Salzburg-Krone
Loading...
00:00 / 00:00
Abspielen
Schließen
Aufklappen
kein Artikelbild
Loading...
Vorige 10 Sekunden
Zum Vorigen Wechseln
Abspielen
Zum Nächsten Wechseln
Nächste 10 Sekunden
00:00
00:00
1.0x Geschwindigkeit
Loading
Kommentare

Willkommen in unserer Community! Eingehende Beiträge werden geprüft und anschließend veröffentlicht. Bitte achten Sie auf Einhaltung unserer Netiquette und AGB. Für ausführliche Diskussionen steht Ihnen ebenso das krone.at-Forum zur Verfügung. Hier können Sie das Community-Team via unserer Melde- und Abhilfestelle kontaktieren.

Kostenlose Spiele
Vorteilswelt